Active Travel Corridor Works

​​​​​​​​​​​​​​We have received the following update from NCC.​​​​​​​

Upcoming roadworks at Station Road as part of the ongoing Bedlington Active Travel Corridor.

As part of the next phase of works, we will be working along Station Road from Chatsworth Drive Roundabout to Jubilee Terrace Junction. We are planning to start these works on Monday 3rd November 2025 and these works are expected to take up to 8 weeks.  To carry out the works safely, we will need to implement a full 24‑hour road closure in small phases. The closure will be staged in sections to maintain, where possible, access for businesses within the works zone. The phases of the road closure and approximate durations are as follows;

  • Phase 1 – Chatsworth Drive Roundabout to Kings fish and chip shop– 3 weeks 
  • Phase 2 – Kings fish and chip shop to the junction of the Co-op car park – 1 week 
  • Phase 3 – Co-op Car Park to Jubilee Terrace. - 4 weeks 

We will begin at the westernmost section, adjacent to the Chatsworth Drive roundabout, and progress eastward toward the level crossing. Please note that Waverly Drive will also be closed at its junction with Station Road for the duration of this phase of works. 

During these works, busses will not be able to access Station Road or Rothesay Terrace and will be diverted via Jubilee Terrace and Stead Lane. 

 

All enquiries to